This checklist was developed to help Project Managers work through the BA development, submittal and review process using the ESA Webtool.  For clarification or a more detailed description of a given step, please refer to the "How To Guide" in the Help Resources menu.  For further clarification, questions can be submitted to ESAWebtool@dot.gov.
| Task | Complete (Y / N)
 | Completed Date/ Deadline | 
| 1.	Set-up |  |  | 
| Create new Online File Cabinet.
 |  |  | 
| Invite project team to Online File Cabinet.  Go to "Team Drawer" and "Add a Team Member."  Hint: Start with Team Members and an alternate Project Manager.  New site users will need to "create an account" to log-in to the Online File Cabinet.
 |  |  | 
| Add important dates or events to the calendar.
 |  |  | 
| 2.	Ongoing File Cabinet Management Activities |  |  | 
| Manage project team.  "Team Members," "Reviewers" and "Project Managers" may be added throughout the BA development, submittal and review process.
 |  |  | 
| Update status table (percent complete and start/end dates).  The information in "File Cabinet Status" will appear in the BA Status Report.
 |  |  | 
| Post events on calendar to help coordinate team (meetings, due dates).
 |  |  | 
| Save important emails as PDF files and upload to "Working" file drawer as part of the administrative record
 |  |  | 
| 3.  Draft BA |  |  | 
| Use National BA Template to create Draft BA document.
 |  |  | 
| Update the "1. Draft BA" step in the Status Table to "in progress" and indicate start/end dates and assignments.
 |  |  | 
| Post events on calendar to help coordinate team (meetings, milestones).
 |  |  | 
| Upload draft BA and other materials to "Working" file drawer to share documents with team. (Project Manager and Authors have access to this drawer)
 |  |  | 
| Change status to "complete" when draft is posted and ready for DOT/FHWA review.
 |  |  | 
| 4.	DOT/FHWA Review |  |  | 
| Add DOT/FHWA Reviewers as "Team Members" (Go to "Team Drawer" and "Add a Team Member").
 |  |  | 
| Update the "2. Review by DOT/FHWA" Status Table step in the status table to "in progress" and indicate start/end dates and assignments.
 |  |  | 
| Notify DOT/FHWA to initiate BA review process. 
 |  |  | 
| Post events on calendar to help coordinate DOT/FHWA review (meetings, due dates).
 |  |  | 
| DOT/FHWA Reviewers upload comments/edits to the "Working" file drawer.
 |  |  | 
| Change the "2. Review by DOT/FHWA" Status Table step in the status table to "complete" when all review comments received.
 |  |  | 
| 5.	Ready to Consult |  |  | 
| Update the "3. BA Ready for Consultation" step in the Status Table to "in progress" when all review comments received. 
 |  |  | 
| Indicate start/end dates and assignments in Status Table.
 |  |  | 
| Post events on calendar to help coordinate incorporation of DOT/FHWA comments. 
 |  |  | 
| Finalize BA documents, upload final files, supporting documents and photos to the "Working" file drawer.
 |  |  | 
| Change the "3. Review by DOT/FHWA" Status Table step in the status table to "complete" when BA document is finalized.
 |  |  | 
| 6.	Submit to Services |  |  | 
| Convert final BA documents to PDF.
 |  |  | 
| Post PDF of BA to the "Consultation" file drawer (200 MB max file upload size).
 |  |  | 
| Post supporting files and photos separately to the "Consultation" file drawer, if necessary.
 |  |  | 
| Add Reviewers to the project team. (Go to "Team Drawer" and "Add a Team Member").  Note: New site users will need to "create an account" to log-in the Online File Cabinet; Reviewers will be able to view, upload, and edit files in the "Consultation" file drawer, but can only view files in the "Completed" file drawer. 
 |  |  | 
| Verify that reviewers have received the invitation to the Online File Cabinet and have successfully logged on/accessed the "Consultation" file drawer.  Note: Only DOT or FHWA has the authority to submit the BA to the Services.
 |  |  | 
| Update the "4. Submitted to the Services" step in the Status Table to "in progress."
 |  |  | 
| Indicate start/end dates and assignments in Status Table (duration should be 135 days).
 |  |  | 
| Upload comments/edits to the "Consultation" file drawer.
 |  |  | 
| Change the "4. Submitted to the Services" step in Status Table to "complete" when Letter of Concurrence (LC) or Biological Opinion (BO) is issued.
 |  |  | 
| 7. LC or BO |  |  | 
| Post LC or BO to "Completed" file drawer.
 |  |  | 
| Change the "5. Letter of Concurrence or BO Issued" step in Status Table step to "complete."
 |  |  | 
| 8.	Re-initiation |  |  | 
| Change the "6. Re-Initiation" step in the Status Table to "in progress."
 |  |  | 
| Post amendments to the "Working" file drawer.
 |  |  | 
|  |  |  | 
| Change the "6. Re-Initiation" step in Status Table step to "complete" once re-initiated consultation complete. 
 |  |  | 
| 9.	Archive |  |  | 
| Ensure all vital information is downloaded to project archives (e.g., Final BA, BO or LC) per agency policy once project is complete.
 |  |  | 
| Redact any site-specific or location specific information contained in final documents saved in the "Completed" file drawer to ensure the continued protection of any listed species in the site vicinity.
 |  |  | 
| Change the "7. Archive" step in Status Table step to "complete" once re-initiated consultation complete.
 |  |  | 
| Exit the Online File Cabinet.
 |  |  | 
| Go back to your list of projects.  Click on the "Edit" button for your project. Change status from "Active" to "Archive" and confirm the "Consultation Type" (informal/formal) is correct. Click "Finish" when done.
 |  |  |