FAST Act - Key Provisions for Project Delivery, June 2016
                    
                        U.S. Department of Transportation
                        Federal Highway Administration
                    
                    
                    Key Provisions
                    A focus on the environmental review and permitting process
                    
                    
                        - FAST Act contains a subtitle on “Acceleration of Project Delivery”
                          
                              - Including  related provisions throughout the Act
 
                          
                         
                        - Multiple  changes, but mostly to already  existing provisions
 
                        - Adds new  procedural requirements to  environmental review process
 
                    
                    
                    Environmental Review for Project Decisionmaking (Sec. 1304) 
                    
                        - §1304 of FAST makes several changes to procedural  requirements of Environmental Review Process 
 
                        - Revises Section 139 of Title 23 a.k.a. “139 Environmental Review Process” “Section 6002 Guidance”
 
                        - Effective December 4, 2015 
 
                    
                    
                    Environmental Review for Project Decisionmaking (Sec. 1304) 
                    Definitions
                    
                        Multimodal Project
                        
                        Redefined as  a project that requires the approval of more than one DOT operating  administration (e.g., FHWA/FTA/FRA) or the secretarial office (OST)
                    
                    
                        Project
                        
                        Redefined to  be consistent with the multimodal definition above but adds considerations for  determining a project – e.g., known sources of Federal funding or financing  identified
                    
                    
                    Environmental Review for Project Decisionmaking (Sec. 1304) 
                    Project Coordination
                    Lead agencies must:
                    
                        - Identify participating agencies no later than 45 days after the NOI or  the initiation of an EA (§ 1304(d)) 
 
                        - Establish coordination plan no later than 90 days after the NOI or  initiation of an EA, which must include a  schedule for completing the  environmental review process. (§ 1304(g)(1)) 
 
                        - Develop a checklist in consultation  with participating agencies, to identify natural, cultural and historic resources in project area. (§ 1304(e)(5)) 
 
                        - Develop an environmental document sufficient to satisfy the requirements for any Federal approval, action, or permit required for the project. (§ 1304(d))
 
                        - Consider and respond to comments received from participating agencies on matters within the special expertise or jurisdiction of those agencies. (§ 1304(c))
                        
 
                    
                    Participating  agencies must:
                    
                        - For all Federal permits and reviews for a project, to the maximum  extent practicable and consistent with Federal law, rely on a single NEPA document  prepared under the leadership of the lead agency. 
 
                        - Provide comments, responses, studies, or methodologies on those areas  within the special expertise or jurisdiction of the agency; and use the process  to address any environmental issues of concern to the agency. 
 
                    
                    
                    Environmental Review for Project Decisionmaking (Sec. 1304) 
                    Project Initiation
                    
                        - Requires a DOT response to a notice from a project sponsor to initiate environmental review (§ 1304(e))
                            
                                - DOT must respond no later than 45 days after project initiation notice
 
                                - "yes," "no," or "need more information"
 
                            
                         
                        - Project sponsor may ask Secretary to designate a USDOT operating administration or office with expertise to serve as the lead Federal agency.	(§ 1304(e))
 
                    
                    
                    Environmental Review for Project Decisionmaking (Sec. 1304) 
                    Alternatives Analysis
                    
                        - Participating agencies’ comments on alternatives must be related to their area of special  expertise or jurisdiction. (§ 1304(f)) 
 
                        - Participating agencies that decline participation in development of  P&N and alternatives must comply with schedule for the project. (§ 1304(f)) 
 
                        - Lead agencies may eliminate alternatives that  have been considered in the planning process so long as certain conditions have  been met. (§ 1304(f)
 
                    
                    
                    Environmental Review for Project Decisionmaking (Sec. 1304) 
                    Issue Identification and Resolution
                    
                        - Any issue resolved by the lead agency with concurrence  of participating agency may not be reconsidered unless significant new  information or circumstances arise (§ 1304(h))
 
                        - Amends financial penalty provisions by adding the  description of date for the application of financial penalties: 180 days from a “complete application,” as  defined by the permitting agency. 
 
                    
                    
                    Environmental Review for Project Decisionmaking (Sec. 1304) 
                    Accelerated Decisionmaking
                    
                        - No changes to procedure, but codifies the use of errata sheets and  single document (FEIS/ROD) 
 
                        - Reemphasizes the use of a  single document (FEIS/ROD), to the maximum  extent practicable (§ 1304(j)) 
 
                        - Continues to allow the use of errata sheets  attached to the Draft EIS in lieu of rewriting the DEIS, subject to certain conditions.
 
                        - Changes to Project Reporting 
                          
                              - Federal agencies participating in the environmental  review or permitting process must provide  information on status and progress of EISs and EAs to  be included in a “searchable internet website” established by the Secretary.  (§ 1304(j)) 
 
                              - Connected to the newly established Federal  Permitting Dashboard (see Title XLI  (41) of FAST)
 
                          
                         
                    
                    
                    Environmental Review for Project Decisionmaking (Sec. 1304) 
                    Programmatic Approaches
                    
                        - Directs the Secretary to allow for the use of programmatic approaches  to conduct environmental reviews (§ 1304(b)) 
 
                        - Secretary shall ensure that programmatic reviews 
                            
                                - Promote transparency 
 
                                - Use accurate and timely information 
 
                                - For tiered analyses, 
                              
                                  - describe the relationship  between programmatic analysis and  any future analysis and
 
                                  - define the role of the  public in the process.
 
                              
                                 
                                - Are available to other  relevant Federal and State agencies, Indian tribes, and the public; and 
 
                                - Provide notice and public comment opportunities
 
                            
                         
                        - Effective after the completion of rulemaking
 
                        - Rulemaking is Congressionally directed to be complete by December 4, 2016
 
                        - Rulemaking requires a 60-day comment period
 
                    
                    
                    Procedural Changes (Sec. 1304)
                    Implementation Summary
                    
                        - Issued Q&As focused on applicability to modes on April 8, 2016
 
                    
                    NEXT STEPS 
                    
                        - Issue In-depth Procedural Q/A’s
 
                        - Issue separate Liaison Guidance focused on Section 1304(i)
 
                        - Update 23 CFR 771/774 with procedural changes through rulemaking
 
                        - Update Section 139 guidance
 
                    
                    
                    New Flexibilities
                    Alignment of §4(f) and §106 Procedures (§1301)
                    
                        - Requires coordination with  DOI and ACHP within 90 days 
                          
                              - Occurred February 5, 2016 
 
                          
                         
                        - Establishes an optional process for historic sites  under Section 4(f) in exchange for multiple, additional concurrence points with  other Federal and State entities 
 
                        - Does not change the substantive requirements of Section  4(f) or preclude DOT from using existing procedures for Section 4(f) and  Section 106 reviews
 
                    
                    
                    New Flexibilities
                    Treatment of certain bridges under preservation requirements (§1303)
                    
                        - Effective October 1, 2015 
 
                        - Exempts common post-1945 concrete and steel bridges or  culverts from individual review under Section  4(f). 
 
                        - In November of 2012, the Advisory Council on Historic  Preservation (ACHP) issued a Program Comment that established the ability to  eliminate individual historic review requirements under Section 106 for these structures. 
 
                        - States for which a inventory has not yet been reported  are not eligible to use the ACHP Program Comment (Nov. 2012) or the Section 4(f) exemption provided by the FAST Act. 
 
                        - Projects with circumstances that could benefit from  the Program Comment and this exemption should be noted in the NEPA documentation. 
 
                    
                    
                    New Flexibilities
                    Treatment of Improvements to Rail & Transit Under Preservation Requirements  (§11502)
                    
                        - Effective December 4, 2015 
 
                        - Exempts from Section 4(f) review the use of railroad  and rail transit lines, or elements thereof, that are in use or historically  used for the transportation of goods  or passengers. 
 
                        - Applies regardless of whether the element is  listed on or is eligible for listing  on the National Register of Historic Places
 
                    
                    Note: This exception does not apply to rail/transit stations and bridges and tunnels located on rail/transit lines not in use.
                    
                    New Flexibilities
                    Railroad Rights-of-way (§11504)
                    
                        - Directs DOT to provide ACHP with a proposed exemption of railroad rights-of-way consistent with the existing exemption for the Interstate Highway System.
                              - Requires completion within 1 year of enactment
                         
                        - Exemption is not available for use until the ACHP has taken action on the proposed exemption.
 
                    
                    
                    New Flexibilities
                    Emergency Exemptions (§1432)
                    
                        - Effective October 1, 2015 
 
                        - Clarifies that certain emergency reconstruction  projects are eligible for emergency exemptions or expedited procedures under specific  environmental laws. 
 
                        - Does not modify any of the existing emergency  procedure processes in place. 
 
                    
                    
                    New Flexibilities
                    Elimination of Barriers for At-risk Bridges (§1439)
                    
                        - Authorizes taking of nesting swallows for  at-risk bridges until the Department of the Interior takes regulatory action to  establish alternative procedure. 
                        
                            - at-risk is defined as a  bridge eligible for funding under title 23, U.S.C., with any component  condition rating of 3 or less. 
 
                        
                         
                        - Effective October 1, 2015 until Department  of Interior issues final rule to authorize the take of nesting swallows to  facilitate bridge repair, maintenance,  or construction activities. 
 
                        - The take period is only  between April 1 and August 1 
 
                    
                    
                    New Flexibilities
                    Encourage Pollinator Habitat and Forage  (§1415)
                    
                        - Effective October 1, 2015 
 
                        - Clarifies that activities to establish and improve pollinator habitat are eligible for Federal funding if related to a  federally eligible transportation project 
 
                        - Administrator released a  letter focused on FHWA efforts 
 
                        - Newly released publication of “Pollinators  and Roadsides: Best Management  Practices for Managers and Decision Makers” 
 
                        - For additional information visit: https://www.environment.fhwa.dot.gov/env_topics/ecosystems/pollinators.aspx
 
                    
                    
                    Refines Existing Procedures 
                    Strengthening Planning and Environmental Linkages (§1305 and §1306)
                    
                        - Effective October 1, 2015 
 
                        - The FAST Act makes some  changes to PEL, most of which are  clarifications from MAP-21. It: 
                      
                          - Adds purpose and need and  preliminary screening of alternatives (including the elimination of  unreasonable alternatives) to the list of  planning decisions that can be used in the environmental review process. 
 
                          - Eliminates the requirement for  concurrence of other participating agencies  within relevant expertise. Replaces it with concurrence of cooperating agencies with responsibility for permitting, review, or approval of the project. 
 
                          - Eliminates the  requirement for approval by the State, relevant MPO, local or tribal  governments where the project is located prior  to “adoption or incorporation by reference” and establishes conditions for which “adoption or incorporation by reference” for a  planning product 
 
                          - Emphasizes the  preference for utilizing programmatic mitigation  plans in future NEPA documents. 
 
                      
                         
                    
                    
                    Refines Existing Procedures 
                    Categorical Exclusion for Projects of Limited Federal Assistance  (§1314)
                    
                        - Effective October 1, 2015 
 
                        - Requires annual adjustments for inflation to the dollar  thresholds for the existing CE for projects with limited Federal assistance 
 
                        - See  23 CFR 771.117(c)(23)
 
                        - Annual adjustments will be posted to the environmental toolkit. 
 
                    
                    
                    Codifies Existing Activities
                    Clarification of Transportation Environmental Authorities  (§1302)
                    
                        - Effective October 1, 2015 
 
                        - Approves the terminology “Section 4(f)” and “Section 106”  as short-hand references to the statutes. 
 
                    
                    
                    Codifies Existing Activities
                    Programmatic Agreement Template  (§1315)
                    
                        - FHWA may enter  into programmatic agreements with a State to allow that State make a NEPA CE certification, or determination and approval on FHWA’s behalf. This applies to CEs that: 
                      
                          - Are specifically listed in  paragraphs (c) and (d) of Section 771.117 
 
                          - Meet the criteria for a CE  under 40 CFR 1508.4 
 
                          - Are identified in the  programmatic agreement 
 
                      
                         
                    
                    CE Agreements are subject  to the conditions in Section 771.117(g), which was clarified under the FAST  Act.
                    CEQ Designation Process
                    
                        - Gather information for substantiation, based on the  State’s experience or other information, to show that such types of actions  typically do not have significant environmental impacts.
 
                        - FHWA consults  with the Office of the Secretary of Transportation  (OST) and CEQ about the new CE(s).
 
                        - FHWA solicits  and considers public comments received through  the required notice-and-comment process, before receiving formal approval by  OST and CEQ.
 
                    
                    
                    Codifies Existing Activities
                    Permitting Process Improvement   (§41003)
                    
                        - Establishes online public access, similar to the  existing permitting dashboard, to publish the status of NEPA & permitting for all covered projects. 
 
                        - All FHWA projects  subject to section 139 of title 23 are excluded from this provision; however  section 1304(j) of FAST does require  a searchable website linked to the dashboard in this provision for various NEPA permitting milestones on all EA and  EIS projects. 
 
                    
                    
                    CE Assignment Program Changes
                    Technical Assistance for States  (§1307)
                    
                        - Effective October 1, 2015 
 
                        - At the request of a Governor, the FHWA must provide to the SDOTs  technical assistance, training, or other support relating to the following: 
                      
                          - assuming responsibility under the CE Assignment Program, 
 
                          - development of an memorandum  of understanding for the CE Assumption Program, or 
 
                          - addressing a responsibility in need of corrective action 
 
                      
                         
                        - Note - Priority will be given to those states  that have waived or are in the process of sovereign immunity waiver under CE  assumption.
 
                    
                    
                    Surface Transportation Project Delivery Program Changes 
                    Audits  (§1308)
                    
                        - The State is required to provide FHWA  with any information it  requests, but that information will be what FHWA reasonably considers necessary to ensure that the State is adequately carrying out  the responsibilities assigned to the State. 
 
                        - The State is solely responsible and  solely liable for carrying out  responsibilities assigned in lieu and  without further approval of FHWA. 
 
                        - The State continues to only assume the USDOT/FHWA environmental review responsibilities  (and not those of any other Federal agency) for individual projects.
 
                    
                    
                    Program for Eliminating Duplication of Environmental Reviews
                    New Pilot Program  (§1309)
                    
                        - Establishes a pilot for NEPA assumption States to substitute State  environmental laws that are “at least as stringent” as NEPA and 23 USC 139, with  the concurrence of CEQ  
 
                        - The State must:
                      
                          - waive sovereign immunity 
 
                          - Participate in the 327 NEPA Assignment Program 
 
                          - Have state law “at least as stringent” as NEPA
 
                      
                         
                        - The provision requires rulemaking that is coordinated with CEQ
 
                        - The program is yet to be established by FHWA and CEQ, but will require:
                            
                                - a state to apply, 
 
                                - public notice on the  application, and 
 
                                - for FHWA and CEQ to review the application to approve or disapprove. 
 
                            
                         
                        - If approved, the State must enter into an agreement for the pilot program  
 
                        - Under this pilot program, legal claims would be filed  in Federal court and decision made by the State under this program would have a 2-year statute of limitations instead of  150 days for NEPA decisions. 
 
                    
                    
                    Program for Eliminating Duplication of Environmental Reviews
                    Implementation Summary  (§1309)
                    NEXT STEPS
                    
                        - Establish Program 
 
                        - Issue rulemaking 
 
                        - Issue guidance 
 
                        - Deliver report to Congress by December 4, 2017 
 
                    
                    
                    Other Provisions to Consider
                    
                        - Application of CEs for  Multimodal Projects (§1310) 
                          
                              - Broadens USDOTs ability  to apply CEs designated under NEPA regulations/procedures  across modes for multi-modal  projects, subject to certain conditions 
 
                          
                         
                        - Accelerated Decision Making  for EIS projects (§1311) 
                          
                              - Codifies MAP-21 changes to the environmental review  process for certain projects under Title 49  (49 U.S.C. 304(a). 
 
                              - The section replaces the current process for adoption  of environmental documents with a new statutory process 
 
                          
                         
                        - Improving State and Federal Agency Engagement in Environmental Reviews (§1312) 
                          
                              - Expands the existing provisions on the use of Federal  funds for liaison positions and to  allow for the involvement of non-State entities. 
 
                          
                         
                        - Aligning Federal  Environmental Reviews (§1313) 
                          
                              - Requires the development of a series of improvements  aimed at aligning the Federal  environmental review process for non 23 U.S.C. 139 projects. This work, led by USDOT, is  to be done in coordination with relevant permitting agencies.
                              
 
                          
                         
                    
                    
                    Additional FAST Act Information