NEPA Implementation
 The Development of Logical Project Termini
   
        November 5, 1993 
    I. Introduction
      In developing a project concept which can be advanced through the stages of planning, environment, 
        design, and construction, the project sponsor needs to consider a "whole" 
        or integrated project. This project should satisfy an identified need, 
        such as safety, rehabilitation, economic development, or capacity improvements, 
        and should be considered in the context of the local area socioeconomics 
        and topography, the future travel demand, and other infrastructure improvements 
        in the area. Without framing a project in this way, proposed improvements 
        may miss the mark by only peripherally satisfying the need or by causing 
        unexpected side effects which require additional corrective action. A 
        problem of "segmentation" may also occur where a transportation 
        need extends throughout an entire corridor but environmental issues and 
        transportation need are inappropriately discussed for only a segment of 
        the corridor. 
      The Federal Highway 
        Administration (FHWA) regulations outline three general principles at 
        23 CFR 771.111(f) that are to be used to frame a highway project: 
      In order to ensure 
        meaningful evaluation of alternatives and to avoid commitments to transportation 
        improvements before they are fully evaluated, the action evaluated in 
        each environmental impact statement (EIS) or finding of no significant 
        impact (FONSI) shall:
      
      
        - Connect logical termini and be of sufficient length to address environmental 
          matters on a broad scope;
 
        - Have independent utility or independent significance, i.e., be usable 
          and be a reasonable expenditure even if no additional transportation 
          improvements in the area are made; and
 
        - Not restrict consideration of alternatives for other reasonably foreseeable 
          transportation improvements. 
         
      
      
     
      The aim of this paper 
        is to discuss criteria that can be used to select logical termini (project 
        limits) for development of a project. The primary discussion will be on 
        the first of the three factors mentioned above. However, all three are 
        interrelated and necessary to the development of an integrated project. 
      
      The remainder of this 
        paper is divided into three sections. Section II will further define logical 
        termini. Section III will discuss several case studies covering factors 
        that can come into play in choosing termini, and Section IV will offer 
        some conclusions. 
 II.  A Definition of Logical Termini 
      Logical termini for 
        project development are defined as (1) rational end points for a transportation 
        improvement, and (2) rational end points for a review of the environmental 
        impacts. The environmental impact review frequently covers a broader geographic 
        area than the strict limits of the transportation improvements. In the 
        past, the most common termini have been points of major traffic generation, 
        especially intersecting roadways. This is due to the fact that in most 
        cases traffic generators determine the size and type of facility being 
        proposed. However, there are also cases where the project improvement 
        is not primarily related to congestion due to traffic generators, and 
        the choice of termini based on these generators may not be appropriate. 
        The next section will show some examples where this is the case. 
      Choosing a corridor 
        of sufficient length to look at all impacts need not preclude staged construction. 
        Therefore, related improvements within a transportation facility should 
        be evaluated as one project, rather than selecting termini based on what 
        is programmed as short range improvements. Construction may then be "staged," 
        or programmed for shorter sections or discrete construction elements as 
        funding permits. 
      III. 
        Sample Project Concepts and Discussion 
      A. Case #1 
      US 22 is a rural two 
        lane facility without access control. A number of high accident locations 
        have been identified, and the need for the project is to correct site 
        specific geometric deficiencies between point A (Route 602) and point 
        B (no intersecting roadway). 
      Discussion: In this 
        case, the selection of A and B as termini is reasonable, given the scope 
        of the project. In fact, for projects involving safety improvements, almost 
        any termini (e.g., political jurisdictions, geographical features) can 
        be chosen to correspond to those sections where safety improvements are 
        most needed. The first criterion, that the project connect logical termini 
        and be of sufficient length to address matters on a broad scope, is largely 
        irrelevant due to the limited scope of most safety improvements. Furthermore, 
        even if other safety improvements are needed beyond those in segment A-B, 
        the project termini need not be expanded to include these other improvements. 
        The other two criteria still need to be met to choose A and B as termini: 
        the safety improvements have independent utility (i.e., they can function 
        as stand-alone improvements without forcing other improvements which may 
        have impacts), and these improvements do not restrict consideration of 
        other reasonably foreseeable transportation improvements (such as major 
        safety improvements in an adjoining section, e.g., point B to Route 604, 
        which could involve changes in alignment of the segment currently under 
        review). Also, all environmental requirements must still be met. For instance, 
        straightening of a curve through parkland cannot take place without completing 
        the necessary section 4(f) analysis. 
      B. Case #2 
      US 26 is on the eastern 
        fringe of a rapidly growing urban area. Over the next 20 years, traffic 
        growth and congestion are predicted for the section of roadway closest 
        to the urban area, between Route 100 and Route 200. Since US 26 also serves 
        as a through facility to points east, congestion will increase on the 
        other sections also. It is proposed to deal with the worst of the congestion 
        problems by widening the road to four lanes between point A (Route 100) 
        and point B (Route 200). 
      Discussion: Widening 
        between point A and point B could be implemented as a reasonable project 
        with logical termini, but several conditions would have to be met: 
     
	 - The project serves 
        an identified need to upgrade US 26 in the suburban area, and stands on 
        its own from point A to point B. 
 
      - The improvement 
        will not force immediate transportation improvements on the remainder 
        of the facility (i.e., the project will not substantially increase congestion 
        or safety problems on the mountainous section of US 26 beyond the problems 
        under the no-build case). If improvements are forced, there could be project 
        impacts severe enough (e.g., 4(f), endangered species) to complicate completion 
        of US 26 in the mountainous section, and this should be investigated now. 
        This would be to see whether alternatives for other foreseeable transportation 
        improvements have been restricted to the point where environmental requirements 
        will be difficult or impossible to satisfy. 
 
      - If there is a demonstrated 
        need for improvements in the entire corridor from point A to point C, 
        there may still be no funding available and no likelihood of improving 
        the entire corridor in the near future. In this case, the project from 
        point A to point B could still be implemented providing the above conditions 
        were met. 
 
      - If there is potential 
        for improvements to the whole US 26 corridor in the near future, and if 
        there may be alternate alignments to satisfy the project need that will 
        change the alignment in the AB section, it would be prudent to evaluate 
        the entire corridor from A to C. Assuming limited funds, the suburban 
        section could be programmed for staged construction first, and subsequent 
        sections could be reevaluated at the appropriate time. However, as long 
        as the AB segment represents a stand-alone project (i.e., all three of 
        the criteria in 23 CFR 771.111(f) are met), there is no environmental 
        requirement to consider the entire corridor in one document. The only 
        issue that needs to be treated with care is to leave enough flexibility 
        in alternative selection in future upgrading of the entire corridor so 
        that environmental requirements can be satisfied (e.g., don't build the 
        AB segment in a way that it would be a "loaded gun" forcing 
        the upgrading to point C to take 4(f) property, which otherwise would 
        have been avoided). 
 
	  
      C. Case #3  
      The proposed project 
        is a new interchange with I-28 at the north edge of a growing urban area 
        with options to upgrade an existing north-south feeder/collector route, 
        Kellogg Rd., on a new location. The next interchange south is at capacity 
        now due to 1) new housing in the north end of town, and 2) a rapidly expanding 
        commercial area at the existing interchange. The identified purposes of 
        this project are to reduce circuitous travel for north end residents and 
        to reduce congestion at the next interchange south. 
      Discussion: At first 
        glance, the logical termini for analysis are the points where the new 
        interchange ties in with existing facilities (Kellogg Rd. and Drury Rd.). 
        Would this action force other project improvements? In this example, Kellogg 
        Rd. and Drury Rd. may be overloaded by interchange traffic. If this is 
        considered now, there may be design options to address this without substantial 
        change or disruption. If this is dealt with later, the options may be 
        more limited. If the only remaining option in the future is to widen Kellogg 
        Rd. and Drury Rd., there may be considerable disruption, relocations, 
        etc., which could possibly have been avoided. For this particular project, 
        the eastern project terminus was the intersection of Coleman St. and Drury 
        Rd., since there was adequate capacity on Drury Rd. to absorb the traffic 
        and no additional improvements would be forced. The western project terminus 
        was further away from the intersection, since Kellogg Rd. did not have 
        enough capacity to handle the traffic from the interchange. The terminus 
        in this case was where Kellogg Rd. intersected with Chris Rd. It was demonstrated 
        that Chris Rd. had the capacity to handle the additional traffic and that 
        no additional improvements would be forced. Options for upgrading Kellogg 
        Rd. included widening of the existing Kellogg Rd. or a north-south feeder 
        road on new alignment. Even if the project sponsor had decided not to 
        upgrade Kellogg Rd., the environmental document should have covered the 
        environmental impacts resulting from the congestion of this route (e.g., 
        community disruption, possible air quality violations). 
      D. Case #4
       This 
        proposed facility is on new alignment, connecting Route 91 with I-17. 
        Alternative 1 is shorter, connecting to I-17 at point A, and alternative 
        2 would tie in further east, at point B. The primary travel on this new 
        facility is to and from points east on I-17. I-17 is four lanes west of 
        point B and six lanes east of point B. Alternative 2 has been designated 
        as the preferred by the project sponsor. Alternative 1 was proposed by 
        a citizen's group to reduce the number of relocations and community disruption. 
        Cost estimates are $50 million for alternative 1 (to tie in at point A) 
        and $63 million for alternative 2 (to tie in at point B). 
      Discussion: It is 
        likely that an incomplete picture of the costs and impacts of alternative 
        1 is being provided by only carrying the analysis as far as point A. For 
        both alternatives, consideration of impacts should continue to point B, 
        or east of B if there are likely to be any weaving or merging problems 
        which will force changes in the facility beyond B. In this example, the 
        four lane section between A and B, if overloaded by alternative 1, would 
        force further improvements on I-17 which would likely have additional 
        impacts. Failure to take this into account would underestimate the cost 
        and overall impacts of alternative 1 and skew decisionmaking. As a result 
        of these factors, if Alternative 1 is considered a reasonable alternative, 
        the discussion of impacts should extend to impacts occurring at point 
        B. If I-17 will be able to handle the increased traffic from alternative 
        1 without widening, then the discussion could simply be a demonstration 
        of that fact. 
     IV. Conclusions
       The aim of this paper 
        has not been to present all possible ways of determining logical project 
        termini, but rather to present a thought process that can be used to make 
        these determinations on a case by case basis. For the vast majority of 
        highway projects, the choice of logical termini will be obvious and non-controversial. 
        For those few major projects where other considerations are important, 
        the termini chosen must be such that: 
		
		- environmental issues 
        can be treated on a sufficiently broad scope to ensure that the project 
        will function properly without requiring additional improvements elsewhere, 
        and 
 
      - the project will 
        not restrict consideration of alternatives for other reasonably foreseeable 
        transportation improvements. 
 
     
	 
	 By following this 
        guidance, proposed highway projects will be more defensible against litigation 
        claims of project segmentation, and decision makers and the public will 
        have a clearer picture of the transportation requirements in the project 
        area and a better understanding of the project purpose and need.