Eco-Logical Peer Exchange: Mitigation Approaches for State DOTs;
March 11-12, 2015
Printer-friendly PDF version of this table ➞
← Back to Peer Exchange Activity Report
Compensatory Mitigation Rule Timeline for Bank or ILF Instrument Approval*
|
Event |
# of Days** |
|
Phase I |
Optional Preliminary Review of Draft Prospectus |
30 |
DE provides copies of draft prospectus to IRT and will provide comments back to the sponsor within 30 days. |
Sponsor Prepares and Submits Prospectus
~DE must notify sponsor of completeness w/in 30 days of submission~ |
Phase II |
Day 1** |
Complete Prospectus Received by DE |
Day 30 |
Public notice must be provided within 30 days of receipt of a complete prospectus |
30 |
|
Day 60 |
30-Day Public Comment Period |
30 |
|
Day 90 |
DE must provide the sponsor with an initial evaluation letter within 30 days of the end of the public comment period. |
30 |
15 |
DE distributes comments to IRT members and sponsor within 15 days of the close of the public comment period. |
|
Sponsor Considers Comments, Prepares and Submits Draft Instrument
~DE must notify sponsor of completeness w/in 30 days of submission~ |
Phase III |
Day 1 |
Complete Draft Instrument Received by IRT Members |
Day 90 |
30-day IRT comment period begins 5 days after DE distributes draft instrument to IRT members |
30 |
90 |
Within 90 days of the receipt of a complete draft instrument by IRT members, the DE must notify the sponsor of the status of the IRT review. |
DE discusses comments with IRT and seeks to resolve issues ~ # of days variable~ |
60 |
Sponsor Prepares Final Instrument ~Sponsor provides copies to DE and all IRT members~ |
Phase IV |
Day 1 |
Final Instrument Received by DE & IRT |
Day 30 |
DE must notify IRT members of intent to approve/not approve instrument within 30 days of receipt. |
30 |
45 |
IRT members have 45 days from submission of final instrument to object to approval of the instrument and initiate the dispute resolution process. |
|
Remainder of time for initiation of dispute resolution process by IRT members |
15 |
Day 45 |
INSTRUMENT APPROVED/NOT APPROVED, or DISPUTE RESOLUTION PROCESS INITIATED |
EPA/Corps draft 4/02/08
Total Required Federal Review (Phases II-IV): ≤225 Days
*Timeline also applies to amendments
**The timeline in this column uses the maximum number of days allowed for each phase.